Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Newmarket
Construction start
Jul 12, 2010(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Feb 15, 2010
  • Construction end4 weeks earlyforecast Oct 31, 2011