Optimization and Automation of Drinking Water Distribution System (study and plan)
Federal contribution
$350,000
Federal share50%
of $700.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Newmarket
- Construction start
- Nov 30, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction start9 months lateforecast Mar 1, 2017
- Construction end6 months earlyforecast Mar 31, 2020