Newmarket watermain condition assessment program
Federal contribution
$375,000
Federal share50%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Newmarket
- Construction start
- Nov 30, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction start9 months lateforecast Mar 1, 2017
- Construction end6 months earlyforecast Mar 31, 2020
Also in Newmarket
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49013 in the federal list. How to read these figures.