Water Distribution Upgrade

Hague, Saskatchewan

completeDrinking WaterCC
Federal contribution
$239,741
Federal share33%

of $719.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 20, 2013
201420152016
Built

Approved 5 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Hague
Construction start
Apr 21, 2014(actual)
Construction end
Dec 18, 2015(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jul 1, 2014

Also in Hague

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27570 in the federal list. How to read these figures.