Back to projects

Town of Hague Arena Floor Upgrades

Hague, Saskatchewan

completeRecreationRNIS
Federal contribution
$486,000
Federal share40%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 9, 2021
20222023
Built

Approved 5 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Hague
Construction start
May 1, 2022(actual)
Construction end
Feb 15, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 1, 2022
  • Construction end7 weeks lateforecast Dec 31, 2022

Also in Hague

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57363 in the federal list. How to read these figures.