Town of Hague Municipal Landfill Closure

Hague, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$102,215
Federal share40%

of $255.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
20212022
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Hague
Construction start
Jun 14, 2021(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2021
  • Construction end4 months lateforecast Aug 31, 2021

Also in Hague

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57148 in the federal list. How to read these figures.