Town of Hague Municipal Landfill Closure
Federal contribution
$102,215
Federal share40%
of $255.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
20212022
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Hague
- Construction start
- Jun 14, 2021(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2021
- Construction end4 months lateforecast Aug 31, 2021
Also in Hague
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57148 in the federal list. How to read these figures.