Renewal of Storm Water Management System and Lagoon

Temagami, Ontario

completeWastewaterCC Top Up
Federal contribution
$333,333
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Municipality of Temagami
Construction start
Nov 16, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Jul 1, 2009