Lagoon cleanout and de-sludge
Federal contribution
$28,810
Federal share48%
of $59.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
20182019
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Temagami
- Construction start
- Aug 1, 2019(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction start2.5 years lateforecast Feb 1, 2017
- Construction end4 weeks earlyforecast Nov 30, 2019
Also in Temagami
- Temagami Water Distribution System Upgrades$1.7M
- Renewal of Storm Water Management System and Lagoon$333.3K
- Community Centre Retrofit$80.0K
- Refurbishment and Upgrades at the Temagami South Water Treatment Plant Including Back-up Generator and Auto-valves$45.6K
- Refurbishment and Upgrades at the Temagami North Water Treatment Plant Including Process Tanks and Auto-valves.$15.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50278 in the federal list. How to read these figures.