Lagoon cleanout and de-sludge

Temagami, Ontario

completeWastewaterCWWF
Federal contribution
$28,810
Federal share48%

of $59.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Temagami
Construction start
Aug 1, 2019(actual)
Construction end
Oct 31, 2019(actual)

Against the original forecast

  • Construction start2.5 years lateforecast Feb 1, 2017
  • Construction end4 weeks earlyforecast Nov 30, 2019

Also in Temagami

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50278 in the federal list. How to read these figures.