Refurbishment and Upgrades at the Temagami North Water Treatment Plant Including Process Tanks and Auto-valves.

Temagami, Ontario

completeDrinking WaterCWWF
Federal contribution
$15,920
Federal share50%

of $31.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Temagami
Construction start
Nov 23, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start10 months lateforecast Feb 1, 2017
  • Construction end12 months lateforecast Dec 31, 2017