Expansion of Centennial Centre and Aquatic Facility

Gravenhurst, Ontario

completeRecreationCC Top Up
Federal contribution
$6.2M
$6,175,716
Federal share33%

of $18.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Gravenhurst
Construction start
Mar 7, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Apr 1, 2010
  • Construction end4 months earlyforecast Feb 28, 2012

Also in Gravenhurst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27678 in the federal list. How to read these figures.