Snider's Bay Bridge Replacement

Gravenhurst, Ontario

completeHighways and RoadsRNIS
Federal contribution
$505,747
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2019
202020212022
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Oct 19, 2020(actual)
Construction end
Apr 1, 2022(actual)

Against the original forecast

  • Construction end3 months lateforecast Jan 12, 2022