Back to projects

Live Stream Equipment in Gravenhurst Town Hall

Gravenhurst, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jan 1, 2023(actual)
Construction end
Nov 1, 2023(actual)

Also in Gravenhurst