Water System Upgrades
Federal contribution
$20,000
Federal share33%
of $60.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 25, 2009
20102011
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Bath
- Construction start
- Aug 15, 2009(actual)
- Construction end
- Mar 20, 2011(actual)
Against the original forecast
- Construction start2 months earlyforecast Oct 30, 2009
- Construction end10 months lateforecast May 31, 2010
Also in Bath
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27789 in the federal list. How to read these figures.