Back to projects

Water System Upgrades

Bath, New Brunswick

completeDrinking WaterCC Top Up
Federal contribution
$20,000
Federal share33%

of $60.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 25, 2009
20102011
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Bath
Construction start
Aug 15, 2009(actual)
Construction end
Mar 20, 2011(actual)

Against the original forecast

  • Construction start2 months earlyforecast Oct 30, 2009
  • Construction end10 months lateforecast May 31, 2010

Also in Bath

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27789 in the federal list. How to read these figures.