Back to projects

Scenic River Lookout

Bath, New Brunswick

completeTourismSCF
Federal contribution
$20,842
Federal share33%

of $62.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 22, 2019
20182019202020212022
Built

Approved 2.2 years before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Bath
Construction start
Oct 1, 2020(actual)
Construction end
Mar 31, 2022(actual)

Against the original forecast

  • Construction start2.3 years lateforecast Jun 4, 2018
  • Construction end5 months lateforecast Oct 31, 2021

Also in Bath