Alarm System Upgrades- Sewage Lift Stations
Federal contribution
$8,333
Federal share33%
of $25.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20122013201420152016
Built
Approved 4.2 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Bath
- Construction start
- Mar 2, 2012(actual)
- Construction end
- Jan 12, 2013(actual)
Against the original forecast
- Construction start5 months earlyforecast Aug 1, 2012
- Construction end8 months earlyforecast Aug 31, 2013
Also in Bath
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27798 in the federal list. How to read these figures.