Construction of an Arts and Cultural Centre
Federal contribution
$8.1M
$8,112,107
Federal share33%
of $24.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Milton
- Construction start
- Jan 6, 2010(actual)
- Construction end
- Mar 28, 2011(actual)
Also in Milton