Facility Energy Improvements

Milton, Ontario

completeVentilationCVRIS
Federal contribution
$1.1M
$1,147,826
Federal share80%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
2022
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Milton
Construction start
Jul 5, 2021(actual)
Construction end
Aug 1, 2022(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Jun 30, 2022