Tremaine Road Widening

Milton, Ontario

completeHighways and RoadsISF
Federal contribution
$4.0M
$4,012,065
Federal share25%

of $16.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 18, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 months earlyforecast May 4, 2010