Material Recovery Facility
Grand Bay-Westfield, New Brunswick
Federal contribution
$208,135
Federal share33%
of $624.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 2, 2009
20102011
Built
Approved 6 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Fundy Region Solid Waste Commission
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 1, 2009
- Construction end17 months lateforecast Oct 31, 2009