Material Recovery Facility

Grand Bay-Westfield, New Brunswick

completeSolid Waste ManagementCC Top Up
Federal contribution
$208,135
Federal share33%

of $624.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 2, 2009
20102011
Built

Approved 6 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Oct 19, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 1, 2009
  • Construction end17 months lateforecast Oct 31, 2009

Also in Grand Bay-Westfield

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27900 in the federal list. How to read these figures.