Inglewood School - Ventilation Upgrades
Grand Bay-Westfield, New Brunswick
Federal contribution
$260,000
Federal share80%
of $325.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
20232024
Built
Approved 2.1 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Jun 27, 2022(actual)
- Construction end
- Oct 14, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 12, 2022
- Construction end8 weeks lateforecast Aug 20, 2022