Wastewater System Improvements

Grand Bay-Westfield, New Brunswick

completeWastewaterSCF
Federal contribution
$395,687
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 4, 2016
201620172018201920202021
Built

Approved 11 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 2, 2016(actual)
Construction end
Jul 31, 2021(actual)

Against the original forecast

  • Construction end16 months lateforecast Mar 30, 2020