Rehabilitation of Old Soo Road

Bruce Mines, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$193,647
Federal share33%

of $580.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Apr 30, 2010(actual)
Construction end
Oct 20, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 15, 2010
  • Construction end6 weeks earlyforecast Nov 30, 2010

Also in Bruce Mines

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27998 in the federal list. How to read these figures.