Reconstruction of a Section of Highway 638 in Bruce Mines

Bruce Mines, Ontario

completeHighways and RoadsRNIS
Federal contribution
$503,250
Federal share60%

of $838.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
2020
Built

Approved 4 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Bruce Mines
Construction start
Sep 30, 2019(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start9 months earlyforecast Jun 30, 2020
  • Construction end10 months earlyforecast Oct 30, 2020