Water and Sewer Extension - Tannery Road

Lunenburg, Nova Scotia

completeWastewaterCC
Federal contribution
$449,800
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
20092010
Built

Approved 6 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Lunenburg
Construction start
Mar 29, 2010(actual)
Construction end
Aug 13, 2010(actual)

Against the original forecast

  • Construction start11 months lateforecast May 1, 2009
  • Construction end8 months earlyforecast Mar 31, 2011