Construction of Municipal Lagoon System

Strasbourg, Saskatchewan

completeWastewaterCC
Federal contribution
$1.0M
$1,030,307
Federal share28%

of $3.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2013
2014201520162017
Built

Approved 4 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Aug 10, 2015(actual)
Construction end
Mar 7, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 20, 2015
  • Construction end3 months lateforecast Nov 30, 2016

Also in Strasbourg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28442 in the federal list. How to read these figures.