Back to projects

Waste Water Treatment Upgrade – Rowan’s ravine Provincial Park

Strasbourg, Saskatchewan

completeWastewaterGIS
Federal contribution
$325,000
Federal share50%

of $650.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 1, 2021(actual)
Construction end
Jan 13, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2021
  • Construction end2 months lateforecast Oct 31, 2021

Also in Strasbourg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61009 in the federal list. How to read these figures.