New Lagoon Evaporation Cell
Federal contribution
$1.7M
$1,724,406
Federal share50%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
20172018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Strasbourg
- Construction start
- Jun 26, 2017(actual)
- Construction end
- Dec 28, 2017(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2017
- Construction end15 months earlyforecast Mar 31, 2019