Back to projects

Waste Water Phase 1 - Lagoon Expansion

Meadow Lake, Saskatchewan

completeWastewaterCC
Federal contribution
$800,000
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Meadow Lake
Construction start
Sep 4, 2009(actual)
Construction end
Sep 5, 2012(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 1, 2009