Highway 11A Interchange Upgrade (Diamond Conversion)

Red Deer, Alberta

completeHighways and RoadsISF
Federal contribution
$9.8M
$9,803,000
Federal share50%

of $19.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 2, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Oct 1, 2009(actual)
Construction end
Oct 12, 2011(actual)

Against the original forecast

  • Construction end9 months earlyforecast Jul 15, 2012

Also in Red Deer

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28474 in the federal list. How to read these figures.