Red Deer Storm Water Infrastructure
Federal contribution
$8.0M
$7,995,769
Federal share80%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
20222023202420252026
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Red Deer
- Construction start
- May 11, 2021(actual)
- Construction end
- Jan 27, 2026(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 1, 2021
- Construction end2 months earlyforecast Mar 31, 2026
Also in Red Deer
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58759 in the federal list. How to read these figures.