City of Red Deer G.H. Dawe Community Centre Expansion
Federal contribution
$15.1M
$15,134,832
Federal share40%
of $37.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 25, 2020
202120222023
Built
Approved 6 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Red Deer
- Construction start
- May 15, 2021(actual)
- Construction end
- Oct 15, 2023(actual)
Against the original forecast
- Construction end3 months earlyforecast Dec 31, 2023
Also in Red Deer
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56643 in the federal list. How to read these figures.