Selective Resurfacing Work on Highway 2

Leduc, Alberta

completeHighways and RoadsISF
Federal contribution
$518,826
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 22, 2010(actual)
Construction end
Jan 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2010
  • Construction end8 weeks earlyforecast Mar 31, 2011