Rehabilitation of Highway 39
Federal contribution
$2.2M
$2,237,000
Federal share50%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 29, 2010
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Aug 17, 2010(actual)
- Construction end
- Nov 4, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 3, 2010
- Construction end5 months earlyforecast Mar 31, 2011
Also in Leduc
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40482 in the federal list. How to read these figures.