Leduc Recreational Centre Performance Arena - Plant Ice Chiller Replacement

Leduc, Alberta

completeRecreationCVRIS
Federal contribution
$199,686
Federal share80%

of $249.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 17, 2021
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Leduc
Construction start
May 3, 2021(actual)
Construction end
Aug 31, 2021(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Aug 6, 2021