Bring water filtration plant up to standard
Saint-Denis-sur-Richelieu, Quebec
Federal contribution
$3.6M
$3,625,000
Federal share25%
of $14.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 21, 2009
2009201120132015
Built
Approved 3 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Régie d'aqueduc Intermunicipale du Bas Richelieu
- Construction start
- Feb 9, 2009(actual)
- Construction end
- Oct 31, 2015(actual)
Against the original forecast
- Construction start12 months earlyforecast Feb 1, 2010
- Construction end4 years lateforecast Oct 31, 2011