Water Systems Upgrade
Saint-Denis-sur-Richelieu, Quebec
Federal contribution
$546,310
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Denis-sur-Richelieu
- Construction start
- May 2, 2022(actual)
- Construction end
- Jun 30, 2023(actual)
Against the original forecast
- Construction start11 months lateforecast May 24, 2021
- Construction end7 months lateforecast Nov 30, 2022