Highway 137 Resurfacing
Saint-Denis-sur-Richelieu, Quebec
Federal contribution
$1.1M
$1,068,908
Federal share37%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 11, 2010(actual)
- Construction end
- Oct 12, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 15, 2010
- Construction end3 weeks earlyforecast Oct 31, 2010
Also in Saint-Denis-sur-Richelieu
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29263 in the federal list. How to read these figures.