HELP Clean Water (Huron Elgin London Project)
Federal contribution
$50.0M
$49,985,307
Federal share28%
of $176.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 1, 2009
200920112013201520172019
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Apr 27, 2009(actual)
- Construction end
- Oct 29, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2009
- Construction end8 weeks lateforecast Aug 31, 2018
Also in London