Wastewater Treatment Plant Flood Protection

London, Ontario

underwayDisaster MitigationDMAF
Federal contribution
$19.8M
$19,800,000
Federal share40%

of $49.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 7, 2020
today
2021202320252027
BuiltForecast

Approved 8 weeks before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Construction start
Jul 15, 2024(actual)
Construction end
Nov 8, 2027(forecast)

Against the original forecast

  • Construction start2 weeks earlyforecast Aug 1, 2024

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52842 in the federal list. How to read these figures.