Wellington Gateway

London, Ontario

underwayPublic TransitPTIS
Federal contribution
$41.6M
$41,639,999
Federal share23%

of $184.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
today
20202022202420262028
BuiltForecast
Program
Public Transit Infrastructure Stream
Construction start
Mar 20, 2023(actual)
Construction end
Mar 31, 2028(forecast)

Against the original forecast

  • Construction start2 weeks earlyforecast Apr 3, 2023

Also in London