Back to projects

Pumping Station Upgrades - East River Environmental Control Centre

Stellarton, Nova Scotia

completeWastewaterCC
Federal contribution
$781,300
Federal share33%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2009
200920102011
Built
Program
Building Canada Fund - Communities Component
Construction start
Oct 12, 2009(actual)
Construction end
Sep 16, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2009
  • Construction end7 weeks lateforecast Jul 31, 2011

Also in Stellarton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28657 in the federal list. How to read these figures.