St Bernard St water and sewer renewal

Stellarton, Nova Scotia

completeDrinking WaterCWWF
Federal contribution
$350,886
Federal share48%

of $737.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Stellarton
Construction start
Jun 1, 2017(actual)
Construction end
Aug 31, 2018(actual)

Also in Stellarton