Acadia Ave Water and Sewer System Upgrade

Stellarton, Nova Scotia

completeWastewaterSCF
Federal contribution
$776,944
Federal share32%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2015
201620172018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Stellarton
Construction start
Aug 8, 2016(actual)
Construction end
Jul 31, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2016
  • Construction end14 months lateforecast Jun 1, 2017

Also in Stellarton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46052 in the federal list. How to read these figures.