Acadia Ave Water and Sewer System Upgrade
Federal contribution
$776,944
Federal share32%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 12, 2015
201620172018
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Stellarton
- Construction start
- Aug 8, 2016(actual)
- Construction end
- Jul 31, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast May 15, 2016
- Construction end14 months lateforecast Jun 1, 2017
Also in Stellarton