Highway 1 - Iron Workers Memorial Bridge (Second Narrows) Rehabilitation

Vancouver, British Columbia

completeHighways and RoadsISF
Federal contribution
$371,000
Federal share50%

of $742.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 28, 2010(actual)
Construction end
Nov 16, 2010(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Nov 30, 2010