Deer Lake Water and Sewer System
Deer Lake, Newfoundland and Labrador
Federal contribution
$493,288
Federal share29%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Deer Lake
- Construction start
- Aug 1, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2009
- Construction end9 months lateforecast Jun 30, 2010
Also in Deer Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29066 in the federal list. How to read these figures.