Rebuilding of southbound Highway 15
Federal contribution
$11.3M
$11,350,000
Federal share50%
of $22.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- May 31, 2010(actual)
- Construction end
- Aug 15, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2010
- Construction end8 months lateforecast Dec 15, 2010
Also in Mirabel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29133 in the federal list. How to read these figures.