Highway 117 Asphalt Repair

Mirabel, Quebec

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,137,500
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jul 14, 2010(actual)
Construction end
Jul 14, 2011(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Aug 1, 2010
  • Construction end9 months lateforecast Sep 30, 2010

Also in Mirabel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29451 in the federal list. How to read these figures.