Heating, ventilation and air conditioning (HVAC) system replacement
Federal contribution
$3.8M
$3,778,767
Federal share80%
of $4.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 22, 2021(actual)
- Construction end
- Jan 31, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 15, 2021
- Construction end3 months lateforecast Oct 30, 2022