Rehabilitation of Coulombe Road
Federal contribution
$1.2M
$1,235,000
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Aug 19, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 15, 2010
- Construction end6 weeks earlyforecast Sep 30, 2010
Also in Saguenay