Nahanni Range Road Upgrades

Watson Lake, Yukon

completeHighways and RoadsISF
Federal contribution
$42,780
Federal share50%

of $85.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 13, 2009
ApprovedJan 28, 2010
2010
Built

Approved 9 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Yukon
Construction start
Sep 14, 2009(actual)
Construction end
Sep 23, 2009(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 1, 2009
  • Construction end5 weeks earlyforecast Oct 31, 2009

Also in Watson Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29283 in the federal list. How to read these figures.